The SE Engine opens with a plain admission: nobody starts a project by writing requirements. Requirements are the second draft. The first draft — the one most programs skip or rush — is figuring out who actually cares about the system and what they think they are asking for. That is Stakeholder Expectations Definition, the first of NPR 7123.1's four system design processes, and the subject of this article.
The process sounds procedural. It is not. Its entire value is diagnostic: done properly, it surfaces the disagreements a requirements document would otherwise hide until integration — or until the customer sees the delivered system and says that is not what they meant.
Who actually counts as a stakeholder
NASA's handbook is deliberately wider than “the customer.” A stakeholder is any group or individual affected by or holding a stake in the product, and the handbook splits them into two categories worth keeping distinct. The customer is whoever is requesting or receiving the product at whatever layer you sit in the product breakdown structure — for a prime, that may be an agency; for a subsystem supplier three tiers down, it may be the integration lead who takes your box. Other interested parties are everyone else whose constraints the customer's needs have to fit inside: maintainers, operators, safety organizations, regulators, even — in the handbook's own example — Congress. They rarely write the requirements, but they can veto the design.
Both groups shift by phase and by project type, which is why the handbook itemizes example stakeholders phase by phase rather than naming them once. Missing one early is not a paperwork gap; it is a design constraint nobody applied.
| Output | What it captures | Used next by |
| Validated Stakeholder Expectations (NGOs) | The agreed-to needs, goals and objectives, with constraints and assumptions identified | Technical Requirements Definition — the next process in this series |
| Concept of Operations | How the system will be operated across life-cycle phases to meet stakeholder expectations | Requirements definition, verification and validation planning, training and operations planning |
| Enabling Product Support Strategies | Special provisions needed for fabrication, test, deployment, sustainment and disposal | Logistics planning and the later product realization processes |
| Measures of Effectiveness | The stakeholder's own success criteria — failure to meet them makes the system unacceptable to them | Requirements validation, and later acceptance |
| Human/Systems Function Allocation | How hardware, software and personnel interact, and who is responsible for what | Design Solution Definition and human factors engineering |
Needs, goals and objectives — before there are any requirements
Before anything is written as a “shall,” the handbook asks for three plainer things: a need (the single problem being solved — not the solution), goals (what must be done to meet that need), and objectives (specific, assessable targets that support a goal). A good objective is specific enough to give direction, measurable, realistically ambitious, and framed around outcomes rather than methods — what the system must achieve, not how. None of the three is a requirement, and none is contractually binding; they exist purely so the customer, the stakeholders and the engineering team reach the same understanding of the problem before anyone starts designing an answer to it.
The traceability discipline starts here, not later. A goal that does not support a stated need, or an objective that does not support a goal, does not belong in the set — and if you can already draw that line at this stage, the requirements that follow inherit it for free.
| What it is | Test of a good one | Typical mistake | |
| Need | The underlying problem, stated without a solution in it | Would still be true if every current technology vanished | Writing the need as the solution someone already has in mind |
| Goal | What success looks like, in the stakeholder's language | A stakeholder recognizes it as theirs, unprompted | Goals that only an engineer would have written |
| Objective | A specific, bounded, measurable outcome | You could tell, afterwards, whether it was met | Objectives with no measure attached — an aspiration in disguise |
The Concept of Operations: writing down how it gets used
The single highest-leverage artifact in this process is the Concept of Operations — ConOps. It is not a requirements document; it is a description, usually time-sequenced, of how the system will actually be operated to meet the expectations just captured, written before any design exists to describe. The handbook is specific about why this matters: walking through scenarios and use cases “often reveals requirements and design functions that might otherwise be overlooked” — the antenna nobody sized for a mission phase that only shows up once you narrate the mission end to end, the maintenance access nobody blocked out until someone describes a servicing scenario in prose.
A ConOps earns its keep by forcing disagreement into the open early, while it is still cheap: two stakeholders who each nodded along to the same written expectation often discover, only once someone narrates a day in the system's life, that they imagined two different systems. That disagreement was always going to surface. The ConOps decides whether it surfaces now, in a workshop, or later, in an integration lab.
Measures of Effectiveness
Alongside the ConOps, the process produces Measures of Effectiveness — MOEs: the stakeholder's own criteria for calling the project a success, stated from their point of view rather than the engineering team's. MOEs are frequently qualitative at this stage — they harden into quantitative, verifiable Measures of Performance only once Technical Requirements Definition takes over, the subject of the next article in this series. What matters here is that the criteria for success are captured in the stakeholder's language before anyone translates them into the engineering team's.
| Property | A usable MOE | An unusable one |
| Whose language | Stated in the stakeholder's terms, about the mission | Stated in engineering terms, about the design |
| Measurable | You can say what instrument or observation settles it | Adjectives: 'adequate', 'robust', 'user-friendly' |
| Independent of solution | Survives a change of architecture | Presupposes the design you happen to be planning |
| Actually discriminating | Two candidate designs could score differently on it | Every plausible design passes — so it decides nothing |
Baselining and validating — with the stakeholders, not for them
Expectations are not finished when they are written down; they are finished when the stakeholders who hold them agree they have been captured correctly. The handbook's sequence is explicit: present the needs, goals and objectives, the MOEs and the ConOps back to the stakeholders at a concept review, formal or informal depending on scale; resolve what does not match; obtain commitment — a signature or its equivalent; and only then baseline the set under change control. Every subsequent change to expectations goes back through that same agreement, not around it.
Skipping the validation step and going straight to baselining what the engineering team believes the stakeholders want is the single most common failure mode this process exists to prevent.
Tailoring: a fourteen-person team has stakeholders too
NASA runs this process against an advisory committee structure, a mission directorate and a formal concept review board. A fourteen-person supplier team runs the same process against a prime's Statement of Work, a set of platform interface control documents, and whoever at the customer actually owns the integration schedule — but it is the same process, not a smaller one. The “customer” is the SOW's author or the program office; “other interested parties” are the platform's existing certification basis, the maintainers who will eventually touch your box, and the prime's own systems team who inherit your interfaces. A ConOps at this scale can be four pages, not forty — but a supplier that skips it because the SOW already “has requirements” is skipping the one step that would have caught a misreading of those requirements before it became a contract change.
The bridge to certification evidence
For readers of our DO-178C series, this is where the ladder that ends in a Stage of Involvement audit actually begins. Baselined stakeholder expectations and the ConOps are the top of the traceability chain: they become the system requirements that a supplier later allocates to hardware and software, and that the software's High-Level Requirements — the artifacts an SOI #1 or SOI #2 reviewer samples — must trace up into. A DO-178C program audits downward from HLRs; it inherits, silently, whatever quality this process produced upstream of software entirely. An SOI reviewer never opens a ConOps document. But an HLR that cannot explain why it exists, or that contradicts what the ConOps says the system is for, is exactly what a weak Stakeholder Expectations Definition process looks like two levels down — and by the time it surfaces at SOI #2, it is a finding, not a workshop conversation.
Frequently asked questions
Is a ConOps the same as a requirements document?
No. A ConOps describes how the system will be used and operated — implementation-free, usually narrative or scenario-based. Requirements are the “shall” statements that follow, developed in the next process, Technical Requirements Definition. Writing requirements straight from a Statement of Work without a ConOps is possible, but it removes the step that would have caught a misunderstanding before it was contractually binding.
Who actually validates stakeholder expectations — the engineering team or the stakeholders?
The stakeholders. The handbook's sequence ends with obtaining stakeholder commitment — signatures or their equivalent — at a concept review, before anything is baselined. An engineering team that validates its own interpretation of the expectations against itself has skipped the one step the process exists to force.
How is a Measure of Effectiveness different from a requirement?
An MOE is the stakeholder's own criterion for success, often qualitative and stated in their language. It is not verifiable against a design the way a requirement is. MOEs harden into quantitative Measures of Performance only in the next process, Technical Requirements Definition — covered in the following article in this series.
If your program's requirements keep drifting because nobody agreed what the system was for before someone wrote the first “shall” — that gap is the one this process exists to close, and it is exactly the kind of work we do. Get in touch.